Project completed
Completed 23 Mar 2022
Project facts
- units
- 328
- buildings
- 1
- Master community
- Jumeirah Village Circle
- DLD area
- Al Barsha South Fourth
- Escrow bank
- Abu Dhabi Commercial Bank (ADCB)
- Zoning authority
- Trakhees
- Start date
- 24 Jan 2019
- Planned completion
- 9 May 2022
- DLD project no.
- 2079
DLD description
Technical description as registered with the Dubai Land Department.
RESIDENTIAL AND COMMERCIAL BUILDING 2B+G+4P+32FLOORS+R WITH RATAIL @ GF
Community guide
Jumeirah Village Circle
Lifestyle, location and IZBA listings in this area.
More from Tiger Properties nearby
- 409
- units
- 1
- buildings
83% completeHandover Dec 2025- 840
- units
- 1
- buildings
Planned handover Dec 2028
Facts on this page come from the Dubai Land Department open data registry and may lag the developer's own updates. Prices, floor plans and payment plans are not part of the registry: ask IZBA for current availability.