CompletedPalm JumeirahBuildings
The Palm Tower
by the Palm - Jumeirah Co.Master developer Nakheel .(p J S C)
Project completed
Completed 30 Nov 2021
Project facts
- units
- 435
- buildings
- 1
- Master community
- Palm Jumeirah
- DLD area
- Palm Jumeirah
- Escrow bank
- Mashreq Bank
- Zoning authority
- Trakhees
- Start date
- 1 Feb 2015
- Planned completion
- 30 Nov 2021
- DLD project no.
- 1603
DLD description
Technical description as registered with the Dubai Land Department.
PROJECT CONSISTS OF MIXED USED (HOTEL & RESIDENTIAL FURNISHES APARTMENT), (3B+LG+G+3P+MECH+47+MECH+R)BUILDING LOCATED IN PALM JUMEIRAH. THE APARTMENTS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE AND BLOCK WITH INTERNAL AND EXTERNAL FINISHES.
Community guide
Palm Jumeirah
Lifestyle, location and IZBA listings in this area.
More from the Palm - Jumeirah Co. nearby
- 321
- units
- 1
- buildings
64% completeHandover Dec 2026- 284
- units
- 2
- buildings
64% completeHandover Dec 2026- 460
- units
- 1
- buildings
57% completeHandover Dec 2026- 76
- units
- 1
- buildings
11% completeHandover Mar 2027
Facts on this page come from the Dubai Land Department open data registry and may lag the developer's own updates. Prices, floor plans and payment plans are not part of the registry: ask IZBA for current availability.