Project completed
Completed 31 Dec 2025
Project facts
- units
- 1,518
- buildings
- 5
- Master community
- Sobha Hartland
- DLD area
- Al Merkadh
- Escrow bank
- Dubai Islamic Bank
- Zoning authority
- Dubai Municipality
- Start date
- 1 Nov 2021
- Planned completion
- 31 Dec 2025
- DLD project no.
- 2447
DLD description
Technical description as registered with the Dubai Land Department.
Commercial and residential Building Basement + Ground floor +5 Podium + 41 typical floor + Service floor + roof. The project designed to have a concrete structure and block with internal and external finishes.
Community guide
Mohammed Bin Rashid City
Lifestyle, location and IZBA listings in this area.
More from Sobha nearby
- 1,354
- units
- 2
- buildings
43% complete- 985
- units
- 1
- buildings
84% completeHandover Jun 2026- 363
- units
- 1
- buildings
47% completeHandover Sept 2026
Facts on this page come from the Dubai Land Department open data registry and may lag the developer's own updates. Prices, floor plans and payment plans are not part of the registry: ask IZBA for current availability.