Under constructionArjanBuildings
Nas 3
by Rabdan Real Estate DevelopmentMaster developer Dubai Properties
Construction progress
94%
Expected handover: 1 Feb 2026
Started 1 Oct 2023
Project facts
- units
- 288
- buildings
- 1
- Master community
- Arjan
- DLD area
- Al Barshaa South Third
- Escrow bank
- Emirates Islamic
- Zoning authority
- Dubai Development Authority (DDA)
- Start date
- 1 Oct 2023
- Planned completion
- 1 Feb 2026
- DLD project no.
- 2760
DLD description
Technical description as registered with the Dubai Land Department.
G+2P+12 ,B is water tank,284 units Residential+Retail.The project designed to have a concrete structure and block with internal and external finishes.
Community guide
Arjan
Lifestyle, location and IZBA listings in this area.
More from Rabdan Real Estate Development nearby
- 170
- units
- 1
- buildings
28% completeHandover Sept 2026
Facts on this page come from the Dubai Land Department open data registry and may lag the developer's own updates. Prices, floor plans and payment plans are not part of the registry: ask IZBA for current availability.