Under constructionJumeirah Village CircleBuildings
The Orchard Place
by Peak Summit DevelopmentMaster developer Jumeirah Village
Construction progress
43%
Started 31 Jul 2023
Project facts
- units
- 418
- buildings
- 2
- Master community
- Jumeirah Village Circle
- DLD area
- Al Barsha South Fourth
- Escrow bank
- First Abu Dhabi Bank (FAB)
- Zoning authority
- Trakhees
- Start date
- 31 Jul 2023
- DLD project no.
- 2629
DLD description
Technical description as registered with the Dubai Land Department.
RESIDENTIAL TOWERS G+4P+2TOWERS (23F+30F) + ROOF.The project designed to have a concrete structure and block with internal and external finishes.
Community guide
Jumeirah Village Circle
Lifestyle, location and IZBA listings in this area.
More from Peak Summit Development nearby
- Under construction
The Orchard Place - Tower C
Jumeirah Village CircleBuildingsFirst Abu Dhabi Bank (FAB)- 196
- units
- 1
- buildings
4% completeHandover Mar 2027 - Not started
The Orchard Bliss - Towers D & E
Jumeirah Village CircleBuildingsFirst Abu Dhabi Bank (FAB)- 400
- units
- 2
- buildings
Planned handover Mar 2028
Facts on this page come from the Dubai Land Department open data registry and may lag the developer's own updates. Prices, floor plans and payment plans are not part of the registry: ask IZBA for current availability.