Construction progress
65%
Started 30 Sept 2023
Project facts
- units
- 130
- buildings
- 1
- Master community
- Mina Rashid
- DLD area
- Madinat Dubai Almelaheyah
- Escrow bank
- Emirates Islamic
- Zoning authority
- Trakhees
- Start date
- 30 Sept 2023
- DLD project no.
- 2678
DLD description
Technical description as registered with the Dubai Land Department.
B+G+5+R Residential, The project designed to have a concrete structure and block with internal and external finishes.
More from Mina Rashid Properties nearby
- 151
- units
- 1
- buildings
11% complete- 163
- units
- 2
- buildings
12% complete- 217
- units
- 3
- buildings
10% complete- 478
- units
- 3
- buildings
19% complete- 155
- units
- 2
- buildings
7% completeHandover Jul 2025- 395
- units
- 4
- buildings
50% completeHandover Nov 2026