Construction progress
56%
Started 19 Oct 2023
Project facts
- units
- 0
- Plots
- 383
- Master community
- Damac Hills 2
- DLD area
- Madinat Hind 4
- Escrow bank
- Emirates NBD
- Zoning authority
- Dubai Development Authority (DDA)
- Start date
- 19 Oct 2023
- DLD project no.
- 2730
DLD description
Technical description as registered with the Dubai Land Department.
384 Nos. G+1+R Villas Villas ,The project designed to have a concrete structure and block with internal and external finishes.
More from Front Line Investment Management nearby
- 0
- units
3% complete- 0
- units
52% complete- 130
- units
- 2
- buildings
Handover date to be confirmed- 0
- units
5% complete- 0
- units
55% complete- 557
- units
- 4
- buildings
1% complete
Facts on this page come from the Dubai Land Department open data registry and may lag the developer's own updates. Prices, floor plans and payment plans are not part of the registry: ask IZBA for current availability.