CompletedDubai Creek HarbourBuildings

Creek Beach - Orchid

Project completed

Completed 30 Sept 2025

Project facts

units
208
buildings
2
Master community
Dubai Creek Harbour
DLD area
Al Khairan First
Escrow bank
Dubai Islamic Bank
Zoning authority
Dubai Development Authority (DDA)
Start date
5 Mar 2022
Planned completion
30 Sept 2025
DLD project no.
2383

DLD description

Technical description as registered with the Dubai Land Department.

Building 1 - G+M+12 - 131 Residential Units Building 2 - G+M+9 - 77 Residential Units

Community guide

Dubai Creek Harbour

Lifestyle, location and IZBA listings in this area.

More from Dubai Creek Harbour nearby

  • Under construction

    Aeon

    Dubai Creek HarbourBuildingsEmirates NBD
    262
    units
    2
    buildings
    20% complete
  • Under construction

    Aura

    Dubai Creek HarbourBuildingsEmirates NBD
    163
    units
    1
    buildings
    20% complete
  • Under construction

    Arlo

    Dubai Creek HarbourBuildingsEmirates Islamic
    434
    units
    1
    buildings
    9% complete
  • Under construction

    Fallow

    Dubai Creek HarbourBuildingsEmirates Islamic
    291
    units
    1
    buildings
    15% complete
  • Under construction

    Khor Beach - Savanna, Cedar, Mangrove

    Dubai Creek HarbourBuildingsDubai Islamic Bank
    595
    units
    9
    buildings
    93% completeHandover Jul 2026
  • Under construction

    Khor Beach - Canopy, Moor

    Dubai Creek HarbourBuildingsMashreq Bank
    444
    units
    9
    buildings
    83% completeHandover Nov 2026