Construction progress
91%
Expected handover: 1 Nov 2024
Started 18 Oct 2021
Project facts
- units
- 827
- buildings
- 1
- Master community
- Arjan
- DLD area
- Al Barshaa South Third
- Escrow bank
- National Bank of Fujairah
- Zoning authority
- Dubai Development Authority (DDA)
- Start date
- 18 Oct 2021
- Planned completion
- 1 Nov 2024
- DLD project no.
- 2313
DLD description
Technical description as registered with the Dubai Land Department.
B+G+5P+1Mech+34 Floors Commercial/ Residential.The project designed to have a concrete structure and block with internal and external finishes.