CompletedDamac HillsVillas

Damac Hills Silver Springs 3

Project completed

Completed 29 Jan 2024

Project facts

units
0
Plots
250
Master community
Damac Hills
DLD area
Al Hebiah Third
Escrow bank
Abu Dhabi Commercial Bank (ADCB)
Zoning authority
Dubai Development Authority (DDA)
Start date
1 May 2021
Planned completion
29 Jan 2024
DLD project no.
2228

DLD description

Technical description as registered with the Dubai Land Department.

258 (G+1+R) Villas Residential. The Villas are designed to have a concrete structure and block with Internal and external finishes.