Project completed
Completed 15 Dec 2024
Project facts
- units
- 351
- buildings
- 1
- Master community
- Damac Hills
- DLD area
- Al Hebiah Third
- Escrow bank
- Abu Dhabi Commercial Bank (ADCB)
- Zoning authority
- Dubai Development Authority (DDA)
- Start date
- 3 May 2022
- Planned completion
- 15 Dec 2024
- DLD project no.
- 2358
DLD description
Technical description as registered with the Dubai Land Department.
G+2P+27+R Residential, The project designed to have a concrete structure and block with internal and external finishes.
More from Damac Crescent Properties nearby
- 606
- units
- 2
- buildings
11% complete- 464
- units
- 1
- buildings
30% complete- 0
- units
53% completeHandover Sept 2024- 0
- units
42% completeHandover Sept 2024- 0
- units
79% completeHandover Dec 2024- 479
- units
- 3
- buildings
13% completeHandover Mar 2027
Facts on this page come from the Dubai Land Department open data registry and may lag the developer's own updates. Prices, floor plans and payment plans are not part of the registry: ask IZBA for current availability.