Under constructionBusiness BayBuildings
Binghatti Jacob & Co. Residences Tower
by Binghatti DevelopersMaster developer Business Bay
Construction progress
23%
Expected handover: 30 Jun 2026
Started 1 Oct 2022
Project facts
- units
- 304
- buildings
- 1
- Master community
- Business Bay
- DLD area
- Business Bay
- Escrow bank
- Sharjah Islamic Bank
- Zoning authority
- Dubai Development Authority (DDA)
- Start date
- 1 Oct 2022
- Planned completion
- 30 Jun 2026
- DLD project no.
- 2480
DLD description
Technical description as registered with the Dubai Land Department.
7B+G+5P+3HC+6MECH+83Floors+FM Floor+5 Penthouse +Roof.The project designed to have a concrete structure and block with internal and external finishes.
Community guide
Business Bay
Lifestyle, location and IZBA listings in this area.
More from Binghatti Developers nearby
- 190
- units
- 1
- buildings
20% completeHandover Dec 2025- 753
- units
- 1
- buildings
24% completeHandover May 2026- 728
- units
- 1
- buildings
Planned handover Aug 2026- 1,584
- units
- 5
- buildings
Planned handover Oct 2026- 3,333
- units
- 4
- buildings
Planned handover Dec 2026
Facts on this page come from the Dubai Land Department open data registry and may lag the developer's own updates. Prices, floor plans and payment plans are not part of the registry: ask IZBA for current availability.